Umgesetzte Investitionen

No.

Facility

&

Year of Work’s Completion

Investor

Boiler / Installation

Steam

output

(power of the boiler house)

Burner (s)

1

Steam Boiler House

1998

„Malta-Decor” A.G. Poznań

2x SEFAKO EOG 8 t steam/h
1x LOOS ZFR 28 t steam/h

44 t steam/h

WEISHAUPT

RGL 70

2

Steam Boiler House

1999

RUDAWA - DEKOR Rudawa

LOOS ULS 10000/13

10 t steam/h

WEISHAUPT RL 60

3

Steam Boiler House

1991

ZAKŁAD BADAWCZO ROZWOJOWY "POLMOS" Konin

BASOE Szwecja 6 t steam/h
SEFAKO E-125 3,5 t steam/h

9,5 t steam/h

POLMOR light fuel & mazout

4

Steam Boiler House

1994

WYTWÓRNIA WYROBÓW TYTONIOWYCH Poznań

2x LOOS ULS-4000

8 t steam/h

WEISHAUPT

RGL 60

5

Steam Boiler House

2005

„WYBOROWA” SA Poznań

2x LOOS ULS-3200/10

6,4 t steam/h

WEISHAUPT GL 40/2-A-TMD

6

Steam Boiler House

1998 & 2004

ZAKŁADY MIĘSNE "BARTEK" Sieraków + Ubojnia w Kłosowicach

LOOS ULS-3200/10                  2 x LOOS UL-S 1600/10

3,2 t steam/h          3,2 t steam/h

WEISHAUPT

RGL 40/2-A      WEISHAUPT

 GL-7

7

Steam Boiler House & proces steam

1998

HOCHLAND POLSKA
Sp. z o.o. Kaźmierz

LOOS ULS-2000/10
RUMIA - BASOE 100

3,0 t steam/h

WEISHAUPT G 7
OILON - gas

8

Steam Boiler House

1997

GMINNA SPÓŁDZIELNIA "SAMOPOMOC CHŁOPSKA" Czarnków

2x EKOMET Pleszew
KP 10/1100

3,0 t steam/h

WEISHAUPT G 7

9

Steam Boiler House

1995

OKRĘGOWA SPÓŁDZIELNIA MLECZARSKA Czarnków

2x CLAYTON EOG

3,1 t steam/h

CLAYTON

10

Steam Boiler House

1999

OKRĘGOWA SPÓŁDZIELNIA MLECZARSKA Chodzież

2x LOOS ULS-3200

6,4 t steam/h

WEISHAUPT RGL40/2-A

11

Steam Boiler House

1996

FABRYKA KSZTAŁTEK STYROPIANOWYCH PROFI-ENAMEL Wronki

LOOS ULS-2600

2,6 t steam/h

WEISHAUPT

GL 7

12

Steam Boiler House

2001

GORZELNIA Komorniki k/Tulec

LOOS UHD-3200

3,2 t steam/h

WEISHAUPT

 RG 8

13

Steam Boiler House

1993

OKRĘGOWA SPÓŁDZIELNIA MLECZARSKA Złotów

2x LOOS ULS-2600/13

5,2 t steam/h

WEISHAUPT

 GL 8

14

Steam Boiler House

1992

ZESPÓŁ SZKÓŁ ROLNICZYCH Poznań

VIESSMANN RU / ND
2x 1070 kW

1,2 t steam/h

KÖRTING VT-5

15

Water Boiler House

1994

AKADEMIA EKONOMICZNA Poznań

2x VIESSMANN Paromat Duplex

2140 kW

WEISHAUPT GL8

16

Water Boiler House

1994

PRZEDSIĘBIORSTWO PKS Poznań

2x VIESSMAN

Paromat Triplex

920 kW

WEISHAUPT G3

17

Water Boiler House

1992

POZTEL A.G. Poznań

2x VIESSMANN Paromat Duplex

740 kW

KÖRTING oil

18

Water Boiler House

1993

DRUKARNIA POZNAŃSKA Poznań

2x SCHAFER DOMOBLOCK

680 kW

KÖRTING gas

19

Water Boiler House

1994

Beiersdorf-Lechia A.G. Poznań

VIESSMANN Paromat Triplex

225 kW

KÖRTING gas

20

Steam Boiler House

2004 / 2005

Zakład Mięsny „SKIBA” w Chojnicach

LOOS U-DH 3200/10

I UL-S 1600

3,2 t steam/h

WEISHAUPT

 GL-7 gas/ oil

21

Steam Boiler House

2002

Zakład Mięsny „MATRO” Rawicz

1 x LOOS UH-D 1600/10

 

1,6 t steam/h

 WEISHAUPT 

oil

22

Steam Boiler House

2002

KRONOSPAN PL Szczecinek

1 x LOOS ZFR-IE 22000/20

22 t steam/h

mazout/oil/gas SAACKE typ SKV G60

23

Process installations

2001

LISNER Sp. z o.o. Poznań

frying installation based on boiler using heating oil

1400 kW

WEISHAUPT

 oil

24

Steam Boiler House

2001

ROLMLECZ Zakład Mleczarski w Poznaniu

2 x LOOS 2600

5,6 t steam/h

oil/gas WEISHAUPT

25

Steam Boiler House

2001

ICT Poland Sp. z o.o. Kostrzyn n/Odrą

2 x LOOS ULS- IE 14000

28 t steam/h

oil/gas

WEISHAUPT

WK -type

26

Water Boiler House

2001

Bazalt Wilków

3 x Euronox Torus

2 x600 kW

240 kW

oil - CUENOD

oil - WEISHAUPT

27

Process installation for waste neutralisation

2000

Zakład  Tworzyw Sztucznych. ERG Pustków

1x JUMEI 14 000

9 MW

gas SAACKE

28

Process installations

2004

Zakł. Chemiczne POLICE

Titanium white calcinating furnaces

2 x 13 MW

2x gas/oil SAACKE

29

Water Boiler House

2002

SEC Szczecin

LOOS UTH-Z 32500 MW x 2

65 MW

4 x SAACKE gas/oil

30

Process installations

2003

AMCOR RENTCH Sp. z o.o. Łódź

Thermal oil system .

Heat exchangers

-

-

31

Process installations

2003

NORDENIA Sp. z o.o. Dopiewo

Thermal oil system for printing machines, extension of the system in paint and solvent store

-

-

32

Process installations & Water Boiler House

2007

GESTAMP Polska Sp. z o.o. Września

Tłocznia blach karoseryjnych

LOOS UNIMAT UT 2500 x 6

Radiant heating system using water at 1200C as heating medium, cooling system for hydraulic & mechanical presses.

2650 kW

WEISHAUPT

G 9/1-D gas

 

33

Process installations & Water Boiler House

2007

GONVARRI Polska Sp. z o.o. Września

Krajalnia blach karoseryjnych

LOOS UNIMAT UT 1350 x 6

Radiant heating system using water at 1200C as heating medium.

1350 kW

WEISHAUPT

G 7/1-D gas

 

34

Steam Boiler House
&
Process installations

2006

POZNAŃ ONION Sp. z o.o. Siekierki Wielkie

LOOS UL-S 1600 x 18

Process steam system.

Heat exchanger vegetable oil/steam

1600 kg steam/h

WEISHAUPT

G 9/1-D-ZM gas

 

35

Process installations

2004

Zakłady Chemiczne LUBOŃ

Gas installation under control of The Office of Technical Inspection

-

-

36

Steam Boiler House

2004

„Delitissue”

Sp. z  o.o. Ciechanów

 

LOOS UL-S 16000 x 20

16 000 kg steam/h

SAACKE gas

GS125-30

37

Water Boiler House

2006

SCHATTDECOR Sp. z o.o. Tarnowo Podgórne

VIESSMANN 285 kW –

1 set

VIESSMANN 105 kW –

 1 set

390 kW

RIELLO

RS 28 TC gas

38

Process installations

2005

Zakłady Mięsne „BARTEK“ w Kłosowicach

Water process installations of 830C; 550C and 400C.

Water process installations of 550C and 25 bar.

Steam process installation.  Compressed air process installations for scorching & dehairing machine and for slaughterhouse offal pneumatic conveying TAJFUN.

-

-

39

Steam Boiler House
&
Process installations

2005

Fabryka Tektury TFP Sp. z o.o. Dziećmierowo k/Kórnika

 

LOOS UL-S 8000/16

8000 kg steam/h

WEISHAUPT

 RG 70

gas

40

Steam Boiler House

(development)

2005 / 2006

Fabryka Papieru „Malta-Decor” A.G. Zakład w Rudawie

 

VIESSMANN

12 000 kg steam/h

WEISHAUPT

RGL 70

gas

41

Steam Boiler House
&
in-site water purification plant 270 m3/h

2006 / 2007

Kompania Piwowarska A.G. Poznań

LOOS UL-SIE 18 t steam/h x 3

54000 kg steam/h

WEISHAUPT

 WK x 3

gas/oil

42

Process installation of paper manufacture

2007

Fabryka Papieru „Malta-Decor” A.G. Zakład w Poznaniu i Zakład w Rudawie

Steam condenser pipelines of DN 200 and smaller for paper facilities made of China

-

-

43

Amic-resisting installation

 

2008

UNILEVER POLSKA A.G. Oddział Żywności Poznań

Process installation for  two  1 200 l/sec efficient  ATLAS COPCO compression  generators & four  Domnik Hunter PNEUDRI air dryers.

-

-

44

Process installations
for
paper production

2008

Fabryka Papieru „Malta-Decor” A.G.

Poznań

Steam condenser system installation for MP3. Steam site assembly for steam boiler house to MP3 workshop.

-

-

45

Steam Boiler House
&
 hot water return supply pipeline exchange

2007

Wielkopolskie Przedsiębiorstwo Przemysłu Ziemniaczanego A.G. Strzałkowo-Staw

LOOS UL-S-IE 5000 x 16

5000 kg steam/h

WEISHAUPT

gas/oil

46

Steam Boiler House

2009

Gospodarstwo Rolno-Hodowlane

GĄSIOREK – FARM

Czerniejewo

Steam generator LOOS DF 1500

1,5 t steam/h

 

WEISHAUPT

gas/oil

47

Process installations

2009

„PRISMADECOR” Sp. z o.o. Głuchołazy

In-site net & gas installation for paper production facilities

-

-

48

Gas Boiler House

2009

Akademia Ekonomiczna

Poznań

 

VIESSMANN

100 kW

GIERSCH

gas

49

Process installations

         2010

Okręgowa Spółdzielnia Mleczarska w Czarnkowie. Zakład Produkcyjny w Chodzieży.

Steam generator & condenser for spray drying tower for powder milk production

-

-

50

Water Boiler House

2010

GESTAMP Polska Sp. z o.o

Września

Tłocznia blach karoseryjnych

Expansion heating system. Water boiler LOOS UT 1400 X  6 UNIMAT installation.

 

1400 KW

WEISHAUPT

gas

51

Process installations

2009

NORDENIA  Sp. z o.o.

Dopiewo

Thermal oil installation supplying printing machine

-

-

52

Steam Boiler House

 

2009

BOLS Sp. z o.o.

Oborniki

LOOS UL-S IE

4000 X 10

4 t steam/h

WEISHAUPT

gas

53

Process installations

          2006

Kompania Piwowarska  A.G.

Poznań

Compressed  air installation of capacity

15 000 m3 /h for processing and beer manufacturing.

-

-

54

Steam Boiler House

 

2007 / 2008

ICT Poland Sp. z o.o.

Kostrzyn nad Odrą

Expansion heating system. Water boiler

 LOOS  ULS-IE 

22 000 x 20

22 t steam/h

WEISHAUPT

gas

55

Process installations

       2010/2011

PRISMADECOR Sp. z o.o.

Głuchołazy

Cooling water system installation for printing machines  PML6

-

-

56

Process installations

2010

Gospodarstwo Rolno – Hodowlane

GĄSIOREK – FARM

Czerniejewo

Process installation related to fur animal food manufacture & transportation machines.

-

-

57

Thermal Oil Boiler House

2008

Odazotownia Grodzisk

Polskie Górnictwo Naftowe

i Gazownictwo A.G.

HOVAL

1800 kW

Riello

gas

58

Steam Boiler House

2008 / 2009

AQUILA Radomsko Sp. z o.o.

LOOS UL-S IE

8000 x 18

8 t steam/h

WEISHAUPT

gas

59

Steam Boiler House

2009 / 2010

REM A.G. Nowogard

Vitomax 200 HS M235

5 t steam/h

Riello

gas / LPG

60

Water Boiler House

2009

COLSON Sp. z o.o. Komorniki

Brötje Eurocondens SGB 120C Gz50 &  radiant  heating system Winterwarm  using gas

170 kW

gas

61

Steam Boiler House

2009

Ali Baba Kebab Poznań

JUMAG

240 kg steam/h

Riello

oil

62

Process installations

2009

UNIQ LISNER Sp. z o.o. Poznań

Compressed air with drier produced by PARKER HANIFINN.

-

 

-

 

63

Process installations

2009

UNILEVER POLSKA A.G. Oddział Żywności Poznań

Assembly of two air cooling units produced by PARKER with freezing water installation from cooling station to compressor room.

-

-

64

Pro-environmental installation

2009

„Malta-Decor” A.G. Poznań

Pro-environmental installation of air system reduction targeted burning

-

-

65

Process installations

2009

Sławski Zakład Przetwórstwa Mięsa  i Drobiu „Balcerzak I”  Sp. z o.o. Sława –Wróblów

Assembly of heating thermal centres  with a capacity of 2 MW

-

-

66

Process installations

2009

UNILEVER POLSKA A.G.

Oddział  Żywności  Poznań

Anti-corrosive technological water pipeline installation welded for new, mayonnaise production line.

-

-

67

Process installations

2009

Zespół Elektrowni

 Pątnów-Adamów-Konin A.G.

Replacing 3 pcs. of oil pumps on the block

No. 6 in power station PAK

-

-

68

Steam Boiler House

(development)

2010

Zakłady  Mięsne

 ŁMEAT-ŁUKÓW  A.G.

Zakład Produkcyjny „Dolina Noteci” w Polanowie gm.  Wyrzysk

VIESSMANN

VITOMAX 200  HS

3,8 t steam/h

DREIZLER

gas

69

Technical project.

Process installations.

Control Instrumentation & Automation

2010

UNILEVER POLSKA A.G. Oddział Żywności Poznań

Palm oil installation and by-pass units, such as vapour , condensate, air, nitrogen, water units.

 

Design & execution of automation and control the unloading process and storage tanks.

-

-

70

Technical project & process installations.

2010

INDYKPOL A.G.

Olsztyn

Spray-evaporative condenser installation L=380 m

DN 150 & DN 80

-

-

71

Technical project & process installations

2010

PROFI-ENAMEL

Wronki

Granulate transport technological installation and foaming agent injection and new forms of new vapour, air, condensate, vacuum and cooling water pipeline system.

-

-

72

Steam Boiler House

(development)

2010

LATTERIA TINIS

Rzepin

VIESSMANN

VITOMAX  200 HS

2,9 t steam/h

RIELLO

gas/light oil

73

Technical project & process installations

2011

AQUILA  WRZEŚNIA  Sp. z o.o.

Zakład we Wrześni,

ul. Objazdowa

spray-evaporative condenser installation for corrugators.

Boiler house  extension.

-

-

74

Technical project & thermal oil boiler house assemble

2011

Przedsiębiorstwo Produkcyjno –

Konsultingowe    ADOB

Poznań

FERROLI

400 kW

RIELLO

light oil

75

Process installations

2011

SCHATTDECOR Sp. z o.o.

Głuchołazy

Gas installation for laminate unit with heating – ventilation unit. Cooling system for laminator cylinders installation.

-

-

76

Technical project & process installations

2011

KRONOPOL Sp. z o.o.

Żary

Thermal oil system for MP2 press. Installation of pumps.

-

-

77

Valves,Control Instrumentation & Automation

2011

VOLKSWAGEN  POZNAŃ

Poznań

Spray paint cabin’s modernization. Softweare & control of cabins

-

-

78

Process installations

2011

UNILEVER POLSKA A.G. Oddział Żywności Poznań

Oil fryers and steam boiler renovation. Soda lye and nitrogen acid installation unit.

-

-

79

Process installations

2011

UNILEVER POLSKA A.G. Oddział Żywności Poznań

Processing water installation and public water system connection.

-

-

80

Valves, Control Instrumentation & Automation

2011

Kompania Piwowarska SA

Browary Książęce  TYCHY

Oxygen regulators installation in burners combustion system in the steam boiler station.

-

-

81

Valves,Control Instrumentation & Automation

2011

Kompania Piwowarska  SA

Browary Książęce  TYCHY

Natural gas and bio-gas co-burning installation in the steam boiler station.

-

-

82

Valves,Control Instrumentation & Automation

2011

AQUILA WRZEŚNIA Sp. z o.o.

Września, ul. Objazdowa

Oxygen regulators installation in burners combustion system in the steam boiler station.

-

-

83

Process installations

2011

UNILEVER POLSKA A.G. Oddział Żywności Poznań

Condensate installation in the pasta production area.

-

-

84

Process installations

2011

Kompania Piwowarska  A.G.

Poznań

Industrial sewage averaging device installation.

 

 

85

Technical project & process installations

2011

Kompania Piwowarska  A.G.

Poznań

Heat recovery from steam boiler station of 54 steam tons /h.

-

-

86

Technical project & process installations

2011

Kompania Piwowarska  A.G.

Poznań

Media measurement system: beer, technological steam, water, carbon dioxide, condensate, compressed air.

-

-

87

Technical project & process installations

2011

Kompania Piwowarska  A.G.

Poznań

Diatomaceous earth tanks transition.

-

-

88

Technical project & process installations

2011

AMICA SA

Wronki

Compressed  air installation

-

-

89

Process installations

2012

NORDENIA Sp. z o.o. Dopiewo

Thermal oil installation dedicated for power supply of laminator and subsequent flexographer unit

-

-

90

Process installations

2012

PEC  WRZEŚNIA A.G.

DALKIA

Września

Cogeneration system installation produced by CATERPILLAR of the capacity 2,5MW

-

-

91

Technical project & process installations

2012

UNIQ LISNER Sp. z o.o. Poznań

Steam supply hub for power system of refreezing unit of fish processing.

 

-

-

92

Process installations

2012

FARMUTIL HS A.G. Śmiłowo

64-810    Kaczory

ul. Przemysłowa  4

Measurement system of steam boiler station.

(steam and condensate)

-

-

93

Process installations

2012

UNILEVER POLSKA A.G. Oddział Żywności Poznań

Connecting to the media filling & packaging machine - SIG Combibloc, Bag In Box and pasteurizer Tetra Pack.

-

-

94

Process installations

2012

UNILEVER POLSKA A.G. Oddział Żywności Poznań

Anti-corrosive technological sewage pipeline installation welded for new cooking unit SILO.

-

-

95

Process installations

2012

UNILEVER POLSKA A.G. Oddział Żywności Poznań

Unload of sterilizer manufactured by Emmepiemme srl and its installation through the side elevation.

Sterilizer connection to the supplies and their communication to the aseptic tank.

-

-

96

Process installations

2012

Kompania Piwowarska A.G. Poznań

Provision, assembly and launch of four systems dedicated for clarity measurement of sweet wort in brewhouse.

 

 

97

Valves,Control Instrumentation & Automation

2012

KRONOSPAN Szczecinek

Sp. z o.o.

Szczecinek ul. Waryńskiego 1

Changing the security automation and control  system of  the boiler LOSS 1 type  ZFR  25000

-

-

98

Process installations

2012

Cargill Animal Nutrition

CARGILL (POLSKA) Sp. z o.o.

64-120 Krzemieniewo

ul. Dworcowa 167

Modernization of steam and condensate installation in the steam boiler house.

-

-

99

Process installations

2012

NORDENIA  POLSKA POZNAŃ Sp. z o.o.

Dopiewo,   ul. Wyzwolenia 34/36

Thermal oil installation dedicated for power supply of laminator and subsequent flexographer unit

-

-

100

Process installations

2012

FARMUTIL HS A.G. Śmiłowo

64-811 Kaczory

ul. Przemysłowa  4

Modernization of steam installation supplying destructors of animal fat manufacturing and meat & bone meal

-

-

101

Process installations

2012

KOMPANIA PIWOWARSKA A.G.

Poznań, ul. Szwajcarska 11

Provision, assembly and launch of water system installation of deoxidized water.

-

-

102

Process installations

2012

KOMPANIA PIWOWARSKA A.G.

Poznań, ul. Szwajcarska 11

Installation of beer waste disposal tank.

-

-

103

Process installations

2012

KOMPANIA PIWOWARSKA A.G.

Poznań, ul. Szwajcarska 11

Process engineering installation of REDS beer.

-

-

104

Process installations

2012

UNIQ LISNER Sp. z o.o. Poznań, ul. Strzeszyńska 38/42

Installation of CIP in the new manufacturing line of fish proceeding.

-

-

105

Technical  expert opinion

2012

VOLKSWAGEN POZNAŃ

Sp. z o.o.

ul. Warszawska 349

Extensiveleak testthe gas installation

-

-

106

Gas Boiler House

2012

Przedsiębiorstwo Produkcyjno–

Konsultingowe ADOB Sp. z o.o.

Poznań, ul. Kołodzieja 11

Modernization of thermal oil installation the steam oil boiler house.

Supply of evaporator of W59 thermal oil.

FERROLI

400 KW

 RIELLO

light oil

107

Container  thermal oil boiler house

2012

NAFTAN Sp. z o.o.

Oleksze 21

17-106  ORLA

Container thermal oil boiler house supply including technical installation approach design of paraffin decontamination.

Boiler  OPX1000

1,163 MW

light  oil /  LPG

108

Brewhouse department

2012

KOMPANIA PIWOWARSKA A.G.

Poznań, ul. Szwajcarska 11

Turnover of water pipe system installation and condensate.

-

-

109

Filtration department

2012

KOMPANIA PIWOWARSKA A.G.

Poznań, ul. Szwajcarska 11

Installation of valves dedicated for beer continuous intake for filtration.

 

-

-

110

Compressor room

2012

KOMPANIA PIWOWARSKA A.G.

Poznań, ul. Szwajcarska 11

 Installation of heat exchangers of air driers in compressor room

 

-

-

111

Bottling  room

2012

KOMPANIA PIWOWARSKA A.G.

Poznań, ul. Szwajcarska 11

Turnover of CIP pipe system installation in the bottling room.

 

-

-

112

Technological installations

2012

KOMPANIA PIWOWARSKA A.G.

Poznań, ul. Szwajcarska 11

Installation of antyscuffing system of bottles wash system.

-

-

113

Process installations

2012

UNILEVER POLSKA  A.G.

Oddział Żywności, Poznań,

ul. Bałtycka 43

Installation of water recovery for „effluent pretreatment plant” of sewage.

 

-

-

114

Process installations

2012

UNILEVER POLSKA  A.G.

Oddział Żywności Poznań,

ul. Bałtycka 43

Media connecting  to the aseptictank

-

-

115

Process installations

2012

UNILEVER

POLSKA  A.G.

Oddział Żywności Poznań,

ul. Bałtycka 43

Culinary steam installation.

-

-

116

Process installations

2012

UNILEVER POLSKA  A.G.

Oddział Żywności Poznań,

 ul. Bałtycka 43

Transfer of wash plant trolleys and media installation.

 

-

-

117

Steam Boiler House

2013

SCHATTDECOR Sp. z o.o.

Tarnowo Podgórne

Steam generator

YUMAG

560 kg steam/h

WEISHAUPT/gas

118

Process installations

2013

SCHATTDECOR Sp. z o.o.

Tarnowo Podgórne

Nitrogen pipeline DN50, 230 m, of the flow capacity of 633Nm3 /h for inerting purposes for the needs of the production process

-

-

119

Process installations

2013

KGHM Polska Miedź A.G.

Oddział Huta Miedzi „Głogów”

Głogów, ul. Żukowicka 1

Design and construction of the oil supply system for the installation of the third heating oil preheater for the Plant’s Fuel Station. Processing capacity 12.5 Mg/h.

-

-

120

Process installations

2013

Kompania Piwowarska SA

Poznań

Filtracja

Connecting of heat exchanger beer/ammonia at the filtration department.

-

-

121

Process installations

2013

PGNiG Zielona Góra

FX Warszawa

Kopalnia gazu ziemnego- ośrodek grupowy

Treatment system for natural gas in the Lisewo natural gas mine.

-

-

122

Technological line

 

2013

VOLKSWAGEN POZNAŃ

Sp. z o.o.

ul. Warszawska 349

Overhaul of the KTL drying line.

-

-

123

Technological line

 

2013

VOLKSWAGEN POZNAŃ

Sp. z o.o.

ul. Warszawska 349

 

Installation of manholes on the FL and CC drying lines.

-

-

124

Technical project & process installations

2013

KRONOPOL ŻARY

Sp. z o.o.

Żary

Thermal oil system for MP2 press. Installation of pumps.

-

-

125

Steam Boiler House

2013

LISNER Sp. z o.o.

Poznań, ul. Strzeszyńska

2 boilers  U-MB  of  LOOS/BOSCH

2 x 2 tons steam/h

WEISHAUPT

gas/oil

126

Process installations

2013

LISNER Sp. z o.o.

Poznań, ul. Strzeszyńska

Automatic marinade preparation, storage and distribution station for herring production line, together with a washing system. Dosing of liquid and powdered ingredients, mixing and heating.

-

-

127

Water Boiler House

2013

LAFARGE KRUSZYWA i BETON Sp. z o.o.

Wytwórnia betonu

Wysogotowo, ul. Grzybowa

 

Renovation ofhot water boiler
anda gas burner

470 kW

RIELLO

gas

128

Process installations

2013

Bonduelle Polska Sp. z o.o.

Zakład Produkcyjny

ul. Kilińskiego 11

88-140 Gniewkowo

Modernization of the boiler supplied steam generators CLAYTON 10 tons of steam / h x 2 sets

-

-

129

Technical project.

Process installations.

Control Instrumentation & Automation

2013

UNILEVER

POLSKA  A.G.

Oddział Żywności Poznań,

ul. Bałtycka 43

Design and execution of the heat recovery system from Atlas Copco compressors Q=360 kW.

Instrumentation, process controls and automation – control system for the heat distribution centre.

-

-

130

Anti-corrosive process installations

2013

UNILEVER

POLSKA  A.G.

Oddział Żywności Poznań,

ul. Bałtycka 43

Execution of process systems made of stainless steel:

- brine system

- ice water system

- process water system

- process steam system.

-

-

131

Process installations & construction work

2013

UNILEVER

POLSKA  A.G.

Oddział Żywności Poznań,

ul. Bałtycka 43

Execution of the central heating system DN125 and the hot service water system with the use of pre-insulated pipes.

-

-

132

Process installations & construction work

2013

UNILEVER

POLSKA  A.G.

Oddział Żywności Poznań,

ul. Bałtycka 43

Execution of the delivery sewage line DN200 for the new sewage pre-treatment plant.

-

-

133

Technical project.

Stainless steel process installations.

Control Instrumentation & Automation

2013

UNILEVER

POLSKA  A.G.

Oddział Żywności Poznań,

ul. Bałtycka 43

Design and execution of the stainless steel process system; design and execution of instrumentation, process controls and automation for the system for water recovery from the mixers.

-

-

134

Stainless steel process installations

2013

UNILEVER

POLSKA  A.G.

Oddział Żywności Poznań,

ul. Bałtycka 43

Installation and connection of utilities to container washing facility. A stainless steel system.

-

-

135

Process installations

2013

SCHATTDECOR Sp. z o.o.

Zakład  w Głuchołazach

ul. gen. Andersa 1

Delivery and installation of flue gas ducts DN 2000 for the regenerative thermal afterburner (RTO) system PLM 7.

-

-

136

Process installations

2013

SCHATTDECOR Sp. z o.o.

Zakład  w Głuchołazach

ul. gen. Andersa 1

Internal gas supply system for process equipment (painting unit 4000 kW, air heaters 52 kW x 4, steam generators YUMAG 320kW x 2 and air handling units 180 kW x 4).

-

-

137

Process installations

2013

SCHATTDECOR Sp. z o.o.

Zakład  w Głuchołazach

ul. gen. Andersa 1

Installation of heater in a new hall for the PLM7.

-

-

138

Process installations

2013

SCHATTDECOR Sp. z o.o.

Zakład  w Głuchołazach

ul. gen. Andersa 1

Cooling system for the PLM7 machine.

-

-

139

Process installations

2013

SCHATTDECOR Sp. z o.o.

Zakład  w Głuchołazach

ul. gen. Andersa 1

System for heat recovery from flue gases downstream of the regenerative thermal afterburner RTO, Q = 800 kW.

-

-

140

Process installations

2013

SCHATTDECOR Sp. z o.o.

Zakład  w Głuchołazach

ul. gen. Andersa 1

Cooling system based on absorptive unit Q=560 kW

and cooling tower

Q = 1500 kW.

-

-

141

Process installations

2013

SCHATTDECOR Sp. z o.o.

Zakład  w Głuchołazach

ul. gen. Andersa 1

Internal process steam distribution system

p= 8 bar.

-

-

142

Process installations

2013

SCHATTDECOR Sp. z o.o.

Tarnowo Podgórne

ul. Sowia  10

Cooling system for the PMD 42 machine. Q= 330 kW.

(chiller and drycooler)

-

-

143

Process installations

2013

SCHATTDECOR Sp. z o.o.

Zakład  w Głuchołazach

ul. gen. Andersa 1

Delivery and installation of flue gas ducts DN 1400 for the regenerative thermal afterburner (RTO) for PLM5 and PLM6.

-

-

144

Process installations

2013

MONDI POZNAŃ Sp. z o.o.

62-070 Dopiewo, ul. Wyzwolenia

Delivery and installation of solvent glue supply system for the gluing machine.

-

-

145

Process installations

2014

„Malta-Decor” A.G. Poznań

Upgrade of supply of the MP-1 machine. New steam and condensate systems.

-

-

146

Heat recovery process installation

2014

SCANENERGI SOLUTIONS A/S

IMPERIAL TOBACCO

Tarnowo Podgórne

Heat recovery system. System for heating of supply water to ZWZ.

-

-

147

Heat recovery process installation

2014

SCANENERGI SOLUTIONS A/S

IMPERIAL TOBACCO

Tarnowo Podgórne

System for heat recovery from condensate of the ESS system.

1 200 kW

-

148

Steam/condensate process installations (technical project & assemble)

2014

FARMUTIL HS  A.G.

Śmiłowo

64-811 Kaczory

ul. Przemysłowa  4

Steel, mobile construction of the steam bridge ( layout and installation).

Steam supply DN 150 and  condensate outlet to the new meat & bone floor drier

 (layout and installation).

-

-

149

Process installations

2014

Xylem Water Solutions Polska Sp. z o.o.

AQUANET  Aglomeracja

Mosina – Puszczykowo

Delivery and technological installation of the potable water ozoning for the city of Poznań (stainless installations DN 25 – DN 150 ).

-

-

150

Process installation at a tissue paper manufacturing plant

2014

ICT Poland Sp. z o.o.

Kostrzyn nad Odrą

ul. Włoska  3

Exchange of cylinders and guide rings in HOOD air heater ramping chambers of MP11 machine

-

-

151

Process installations

2014

SCHATTDECOR Sp. z o.o.

Zakład w Głuchołazach

ul. gen. Andersa 1

Varnish and raw material process installation for manufacturing furniture laminates, with a selection and installation of modern CORIOLIS metering and dosing systems – 32 receiving points

-

-

152

Compressed air system

(Concept, detailed design, implementation)

2014

ARDAGH GLASS A.G.

63-800 Gostyń

ul. Starogostyńska 9

Construction of a compressed air system at a plant, from DN 100 to DN 450

-

-

153

Process installations

2014

LISNER Sp. z o.o.

Poznań, ul. Strzeszyńska

Zakład w Kaliszu

Installation of the GA VSD 15 FF compressor by ATLAS COPCO, with a capacity of 2.91 m3/min, together with a tank and auxiliary system in a compressor station.

-

-

154

Process installations

2014

KRONOPOL ŻARY Sp. z o.o.

68-200 Żary

ul. Serbska  56

Construction of a medium-pressure gas path for the burner of a vertical drying station (h=30m)

-

-

155

Process installations

2014

UNILEVER

POLSKA  A.G.

Oddział Żywności Poznań,

ul. Bałtycka 43

Pressure sewer system for process sewage: DN200 (welded PP), DN80 (INOX) for an in-house sewage treatment plant.

-

-

156

Process installations

2014

UNILEVER

POLSKA  A.G.

Oddział Żywności Poznań,

ul. Bałtycka 43

Alternate distribution and automatic reversal system for vegetable oils: soybean/sunflower/rape. Palm oil distribution system. Auxiliary systems: oil tank heating system, process steam, nitrogen, compressed air, process piping system. Tank relocation:

3 x 50 m3. Construction works and electrical systems at the oil pumping station.

-

-

157

Industrial boiler house

2014

ABP Poland Sp. z o.o.

62-045 Pniewy

ul. Wspólna  1

Re-launch of a steam boiler station after a 6 years' shutdown.

LOOS U-HD

1,3 MW x 2

WEISHAUPT

gas and

gas/oil

158

Concept, detailed design and construction of a process system and industrial boiler house together with relevant automatic systems

2014

AQUILA BRZEG Sp. z o.o.

62-300 Września

ul. Objazdowa 6a

 

Cardboard production plant in Skarbimierz/Brzeg

Construction of a steam boiler house. Construction of installations for the cardboard machine.

Construction of relevant installations at the cardboard machine room. Construction of a compressor station with relevant systems, construction of a glue laboratory with relevant systems. Construction of steel supporting structures for pipelines.

Design and construction of automatics and control systems.

Start-up.

8 tons of steam/h

WEISHAPUT

gas

159

Automatics and control systems

2014

UNILEVER

POLSKA  A.G.

Oddział Żywności Poznań,

ul. Bałtycka 43

Replacement of automatics and control systems for vegetable oil installations: soybean, sunflower, rape and palm.

-

-

160

Process installations

2014

VOLKSWAGEN POZNAŃ

Sp. z o.o.

Poznań

ul. Warszawska 349

Inspection and adjustment of 68 burners during shutdown of a coating station.

-

-

161

Process installations

2014

VOLKSWAGEN POZNAŃ

Sp. z o.o.

Poznań

ul. Warszawska 349

Inspection and leak testing of a 19 km gas system in Z1 and Z4 plants of the VW Group

-

-

162

Process installations

2014

Przedsiębiorstwo Produkcyjno–

Konsultingowe ADOB Sp. z o.o.

Poznań, ul. Kołodzieja 11

Zakład we Wrocławiu

Transfer of steam and water piping.

-

-

163

Boiler House

2014

Instytut Ochrony Roślin

Poznań

ul. Miczurina 20

Modernization of a boiler house and boiler automatic systems.

PAROMAT SIMPLEX

895 KW x 2

WEISHAPUT

gas

164

Process installations

2014

FARMUTIL HS  A.G.

Śmiłowo

64-813 Kaczory

ul. Przemysłowa 4

Installation of gas measurement systems for waste disposal cost optimisation.

-

-

165

Process installations

2014

UNILEVER

POLSKA  A.G.

Oddział Żywności Poznań,

ul. Bałtycka 43

Water supply and drainage systems in a new microbiology and physical chemistry laboratory.

-

-

166

Process installations

2015

ARDAGH  GLASS A.G.

63-800 Gostyń

ul. Starogostyńska 9

Construction of gas network from the pressure regulating and metering station to the production hall

-

-

167

Design and execution of process installation as well as control and measurement instruments and automation

2015

SCHATTDECOR Sp. z o.o.

Tarnowo Podgórne

ul. Sowia 10

 

Zakład w Głuchołazach

ul. gen. Andersa 1

Raw material and paint installation with automatics and cabling for 5 new tanks in the raw material and paint warehouse.

-

-

168

Design and execution of control and measurement instruments and automation

2015

SCHATTDECOR Sp. z o.o.

Tarnowo Podgórne

ul. Sowia 10

 

Zakład  w Głuchołazach

ul. gen. Andersa 1

Comprehensive automatic systems, control systems as well as paint and raw material data archiving systems along with metering, software configuration and start-up.

-

-

169

Process installation as well as control and measurement instruments and automation

2015

LISNER Sp. z o.o.

Poznań, ul. Strzeszyńska

Extension of the colouring solution system along with software and technological process control system.

-

-

170

Process installations

2015

KRONOPOL ŻARY Sp. z o.o.

68-200 Żary

ul. Serbska  56

Execution of strength calculations for an existing pipeline for the purpose of replacing heating oil medium with saturated vapour. Redevelopment of a thermal system including reconstruction of heat exchanger.

-

-

171

Process installations

2015

KRONOPOL ŻARY Sp. z o.o.

68-200 Żary

ul. Serbska  56

Execution of condensate system and sections of steam pipeline between adhesive production plant and MDF line.

-

-

172

Process installations

2015

ARDAGH  GLASS A.G.

63-800 Gostyń

ul. Starogostyńska 9

Disassembly of a gas pipeline on the pipe rack.  Execution of a compressed air collector.

-

-

173

Process installations

2015

VPK  Sp. z o.o.

62-300 Września

ul. Objazdowa 6a

 

Zakład w Radomsku

Installation of a new compressor, new compressed air tank, separator and filters. Connection of compressed air system and supply of pump system.

-

-

174

Automatics and control systems

2015

MALTA-DECOR

Poznań, ul. Wołkowyska

Execution of stationary water meters for 4 deep bore wells

-

-

175

Process installations

as well as control and measurement instruments and automation

2015

MALTA DECOR Sp. z o.o.

SWISS KRONO GROUP

Poznań, ul. Wołkowyska 28

Replacement of steam and condensate system for heads no. 1, 3, 4 and 5 of the MP1 paper machine.

Upgrade of MP1 control adjustment system

-

-

176

Process installations

2015

MONDI ŚWIECIE SA

86-100 Świecie

ul. Bydgoska  1

Removal of old exchangers for sodium hydroxide and backwash wastewater; installation of new exchangers.

Construction of 120 m stainless steel piping (DN250).

Construction of support structures and installation of shut-off valves and three-way valves (DN250).

-

-

177

Process installations-

cooling plant

2015

Poznań City Center

Centrum Handlowe przy dworcu PKP w Poznaniu

Replacement of a section of DN500, DN400 and DN200 cooling system. Removal of welding defects in existing joints together with joint replacement report and 100% radiographic inspection.

-

-

178

Process installations

2015

UNILEVER POLSKA SA

Oddział Żywności

Poznań

ul. Bałtycka  43

Construction of raw water and treated water systems

-

-

179

Process installations

2015

UNILEVER POLSKA SA

Oddział Żywności

Poznań

ul. Bałtycka  43

Upgrade of in-house fire protection system

-

-

180

Process installations

2015

MONDI POZNAŃ Sp. z o.o.

62-070 Dopiewo

ul. Wyzwolenia 34/36

Thermal oil system for printing machine no. 205.

 

 

181

Process installations

2015

MONDI POZNAŃ Sp. z o.o.

62-070 Dopiewo

ul. Wyzwolenia 34/36

Execution of thermal insulation for thermal oil system together with exchangers and fittings in M205 machine

-

-

182

Design and construction of stainless steel process system along with control and instrumentation-related works

2015

SCHATTDECOR Sp. z o.o.

Zakład w Głuchołazach

ul. gen. Andersa 1

Execution of paint temperature control system.

Extension of cooling system for POLYTYPE system

-

-

183

Process installations

2015

ARDAGH GLASS SA

63-800 Gostyń

ul. Starogostyńska 9

Overhaul of compressed air system in compressor room no.3.

Overhaul of gas system from DN300 collector to pressure reducing station of W1 glass furnace.

-

-

184

Process installations

2015

GETINGE IC PRODUCTION POLAND Sp. z o..

62-064 Plewiska

ul. Szkolna 30

Construction of steam and condensate system in the Komorniki plant

-

-

185

Process installations

2015

ARDAGH GLASS SA

63-800 Gostyń

ul. Starogostyńska 9

Construction of the plant's gas system.Overhaul of gas connections to the production area and water boiler station.

-

-

186

Process installations-

pressure boosting station

2016

VOLKSWAGEN POZNAŃ

Poznań, ul. Warszawska

Dismantling of the entire water boosting station operating with deep-well pumps.New placement of Behncke bed filter and aerator.Replacement of the filter bed in new and old filters.Construction of new piping system including the replacement of multi-way valves.System start-up, measurement-taking and preparation of as-built documentation.

-

-

187

Process installations

2016

UNILEVER POLSKA SA

Oddział Żywności

Poznań, ul. Bałtycka  43

Construction of process drainage system made from DN200 and DN150 acid-resistant steel.

-

-